Backoffice Outsourcing Malaysia / Legal Outsourcing/IT Outsourcing/HR Outsourcing/Finance Outsourcing/ Call Center Outsourcing

Does Termination Relieve A Contractor For Pre-termination Delay?

October 23, 2024

In law, termination does not take away a plaintiff’s right to claim Liquidated and Ascertained Damages (“LAD”) accrued in respect of pre-termination delay unless expressly stated in the contract.  That is, in the absence of express contractual provisions, termination does not relieve a contractor’s liability for LAD accrued in respect of pre-termination delay.

In PWC Bina Sdn Bhd v Ideal City Development Sdn Bhd [2022] MLJU 519 (“PWC Bina”), the contract provided for LAD between the period from the extended completion date and the date of practical completion. The plaintiff argued that the arbitrator had wrongfully re-written the contract by allowing the defendant to claim LAD for the period between the extended completion date to the date of termination of the contract and therefore, the arbitral award ought to be set aside.

Lim Chong Foong J (as he then was) held that the arbitrator was not plainly wrong:

“It is common ground that the Plaintiff’s proposition is indisputable in a typical completed contract. However, this is a terminated contract mid-stream before completion is achieved. In the circumstances, I am of the view that the Arbitrator’s finding is not plainly wrong and unacceptable. A similar result has been achieved in the recent English Supreme Court case of Triple Point Technology Inc v PTT Public Company Limited [2021] UKSC 29 akin to the circumstances here where the contractual provisions did not expressly provide for a terminated contract scenario.”

In Triple Point Technology Inc v PTT Public Company Limited [2021] UKSC 29 (“Triple Point v. PTT”), PTT entered into a software contract with Triple Point whereby Triple Point was to provide and install certain software for PTT. Article 5.3 of the contract stipulates that:

“If CONTRACTOR fails to deliver work within the time specified and the delay has not been introduced by PTT, CONTRACTOR shall be liable to pay the penalty at the rate of 0.1% (zero point one percent) of undelivered work per day of delay from the due date for delivery up to the date PTT accepts such work…”

A dispute occurred between the parties and PTT terminated Triple Point before the project was completed. Triple Point sued PTT at the TECHNOLOGY AND CONSTRUCTION COURT (“TCC”) for unpaid invoices. PTT counterclaimed for breach of contract and LAD. TCC allowed PTT’s claim for LAD.

At the UK Court of Appeal (COA), TCC’s decision on the LAD. The COA held that although Triple Point did not complete the project on time, PTT was not entitled to claim LAD because PTT did not “accept” the (uncompleted) work as per Article 3.5.

The UK Supreme Court (SC) reversed COA’s decision and held that PTT was contractually entitled to claim LAD for pre-termination delay irrespective of whether PTT had accepted the unfinished work, and that this accrued right to LAD cannot be taken away unless expressly provided for in the contract. According to the SC, termination does not take away the accrued rights unless the contract expressly stipulates so. SC further added that the COA’s interpretation of Article 5.3  LAD is only claimable if the incomplete work were “accepted” by PTT) is inconsistent with commercial reality and the accepted function of LAD.

According to the SC, whether an employer is contractually entitled to claim LAD for pre-termination delay is a matter of construction of the contract as opposed to a matter of principle. The SC stated that a contractor can still be held liable for liquidated and ascertained damages (“LAD”) even if the contract was terminated (prior to the completion of the project).

💣𝗛𝗥 𝗠𝘆𝘁𝗵 #2: “𝗘𝘅𝗽𝗲𝗿𝗶𝗲𝗻𝗰𝗲𝗱 𝗵𝗶𝗿𝗲𝘀 𝗱𝗼𝗻’𝘁 𝗻𝗲𝗲𝗱 𝗼𝗻𝗯𝗼𝗮𝗿𝗱𝗶𝗻𝗴”
2025… ARE YOU READY?
Amendments to the Personal Data Protection Act (PDPA) 2010
What Small And Medium Enterprises (SMEs) Must Look Out For In The Occupational Safety & Health Act (OSHA) 1994 & The Amendment Act 2022?
KRA, KPI, & SMART Goals
Small Business Owners (SBO) and the SIX biggest challenges?
How Time Flies! SMEs, Watch Out!!
CYBER SECURITY ACT 2024 (ACT 854)
EPF (Amendment) Act 2025 : Mandatory EPF Contributions for Non-Malaysian Employees
New to Human Resources? New role? Fresh out of college? Promoted to HR?
Time and Contracts: A Deep Dive into CERAMTEC v ICONIC MEDICARE
10 Data Loss Prevention (DLP) Best Practices for SME Clients to Protect their Sensitive Corporate Data
Do You Need a Data Protection Officer in Malaysia?
The Perils of Poorly Drafted Contracts
💣 𝗛𝗥 𝗠𝘆𝘁𝗵 #1 “𝗪𝗲’𝗿𝗲 𝘁𝗼𝗼 𝘀𝗺𝗮𝗹𝗹 𝘁𝗼 𝗻𝗲𝗲𝗱 𝗛𝗥 𝗽𝗼𝗹𝗶𝗰𝗶𝗲𝘀.”
Is Compliance a headache for the Small and Medium Enterprise (SME) especially during holiday seasons?
💣𝗛𝗥 𝗠𝘆𝘁𝗵 #3: “𝗣𝗲𝗼𝗽𝗹𝗲 𝗼𝗻𝗹𝘆 𝗹𝗲𝗮𝘃𝗲 𝗳𝗼𝗿 𝗯𝗲𝘁𝘁𝗲𝗿 𝗽𝗮𝘆”
🧨 Myth #4: “𝗬𝗼𝘂 𝗰𝗮𝗻’𝘁 𝗯𝗲 𝗳𝗿𝗶𝗲𝗻𝗱𝘀 𝘄𝗶𝘁𝗵 𝘆𝗼𝘂𝗿 𝘀𝘁𝗮𝗳𝗳…“
HR Myth#5: “HR is the boss’s job…we don’t need a dedicated person.”
HR Myth#6: “If they really want the job…they’ll accept any offer.”
January 2, 2025
January 2, 2025

About Company

Cut Cost and Manage better with StarBPO. Get Experts
to handle all the boring stuff of running a business.
Focus on building your business